BHP
Port Hedland
Port Debottlenecking
BHP saw the speed in which Grounded had progressed the MGM camp and requested us to perform this at short notice. The scope involved:
- Complete onboarding and training for project team to become BHP inducted. This was a rigorous and complex process that BHP commended us on achieving in the time we took.
- Design of a new 7 module office and ablution blocks
- Demolition and disposal of existing office and ablution block
- Refurbishment works of existing buildings
- Fabrication of new 7 module office and ablution block
- Transportation and unloading of buildings and materials
- Installation, testing and commissioning of new 7 module office and ablution block
- Provision of MDRs and As-Built Documentation